On a fit-out, the floor is one line item that can quietly wreck a programme. Wrong wear layer for the traffic, a batch shortfall mid-install, missing documentation at handover — each one costs days you do not have. Sourcing SPC for contract work is less about the lowest square-metre price and more about a supplier who can hold spec, supply, and paperwork together. Here is what matters.

Room scene with Omara Exclusive EIR rigid-core SPC flooring by MILAT Floor
Omara, Exclusive EIR — one of 54 MILAT Floor designs.

Match the wear layer to the traffic

Residential-grade SPC will not last in a shop, clinic, or office corridor. For commercial footfall you want the top wear rating and a surface built for it. MILAT's Triollo EIR runs at AC5 — the maximum wear class — with an embossed-in-register surface that holds up to heavy commercial traffic. Specifying to the traffic level up front is cheaper than replacing a worn zone in year two.

Waterproof is non-negotiable in wet zones

Washrooms, kitchens, entrances, and back-of-house areas see water daily. A 100% waterproof SPC core will not swell or delaminate the way an MDF-core product can. MILAT's SPC core is fully waterproof, which keeps one product family running across dry and wet areas of the same fit-out instead of mixing systems.

Acoustic and comfort ratings

Multi-tenant and multi-storey jobs often carry impact-sound requirements. An integrated acoustic backing saves you specifying a separate underlay and simplifies the build-up. MILAT bonds IXPE acoustic backing rated up to 21 dB, and the click system is a licensed Unilin — a known, installer-friendly locking mechanism.

Consistent supply across phases

Fit-outs run in phases, and a floor that matches in phase one but drifts in phase three is a visible defect. Sourcing from a single manufacturer with batch control protects colour and texture continuity across a long programme. Confirm batch consistency and reserve stock for phased delivery when you brief the supplier.

What specifiers will ask you for

RequirementWhat to have ready
Indoor air qualityFloorScore certificate
EU market complianceCE declaration under EU 305/2011
Quality managementISO 9001
Product traceabilitySHI Product Passport
Wear performanceAC5 wear class confirmation

Having this pack ready avoids the last-minute scramble before handover. MILAT supplies FloorScore, CE, the ISO family, and SHI Product Passport documentation for submittals.

Surface texture of the Salis design — rigid-core SPC plank by MILAT Floor
The Salis decor up close.

Custom where the brief demands it

Contract work sometimes calls for a specific colour to match a brand palette or a plank size to suit a setting-out grid. As a manufacturer, MILAT offers custom colours and sizes rather than forcing your design to fit a fixed catalogue — useful when an architect has already committed to a look.

If you have a fit-out coming up, send the spec and traffic level and MILAT will confirm the right product, documentation, and supply plan. Email sales@milatfloor.com or call +90 535 960 79 46 for samples and a project quote.

Sequence deliveries to the programme, not the price break

Buying the whole project's flooring in one drop looks efficient until it sits on site for months. Flooring wants to arrive close to its install window: late enough that ceilings, painting and wet trades are done above it, early enough for acclimatisation and inspection. On phased projects, align deliveries to floor-by-floor handovers and agree the schedule with the manufacturer at order stage, so production is planned as one campaign even if shipping is staged. That single conversation preserves batch consistency while sparing you the storage, insurance and damage risk of a site full of pallets.

Site storage and conditions before the first plank

SPC is forgiving, but it is not indifferent. Store cartons flat, fully supported, in closed dry rooms, never on end and never in unheated containers through temperature extremes. Before installation, the building should be at normal service temperature with windows glazed and wet trades finished; installing into a cold shell and then firing up the heating asks the floor to absorb the building's shakedown. Check screed moisture with proper testing rather than judgement, and record the readings. Those two lines in your site diary are what stand between you and a blame dispute if anything moves later.

Protecting the finished floor from the trades behind you

On most fit-outs the flooring is installed before the last trades leave, and that gap is where new floors get wrecked. Protection is cheap compared to replacement, so make it a line item, not an afterthought.

  • Cover walk routes with taped hardboard or protection sheets, not loose plastic that traps grit
  • Ban scissor lifts and loaded pallet trucks on the finished surface unless load-spreading boards go down first
  • Keep protection on until practical completion, and photograph the floor when it goes down and when it comes up
  • Brief following trades in the induction: paint, adhesive and mortar drops cost the person who made them

Handover: the ten-minute package that prevents callbacks

A flooring handover file costs you ten minutes and saves the first year of phone calls. Include the care and cleaning guidance so the facilities team does not wax or steam a floor that needs neither, the batch numbers actually installed in each zone, and a sensible quantity of attic stock from the same batches for future repairs. Add the acoustic and wear-class documentation the building manager will need for tenant queries. Contractors who hand this over look professional at the exact moment the client is forming their lasting impression.

Use the factory's technical team before problems, not after

A manufacturer's technical department is a free consultancy most contractors only call when something has gone wrong. Invert that. Send the floor build-up, screed type, heating design and traffic expectations before you order, and let the factory confirm the product choice and installation approach in writing. When a manufacturer like MILAT has engineered the whole system, core, licensed Unilin click, attached IXPE layer, that written confirmation also consolidates responsibility: one party stands behind the plank and its installation guidance, which is exactly the position you want if a dispute ever surfaces.

Talk to MILAT Floor

Samples, specifications, OEM & private label, wholesale or export — our team is ready.

Contact Us

FAQ

Frequently asked questions

What wear class do I need for commercial fit-out?

For heavy commercial traffic, specify AC5 — the highest wear class. MILAT's Triollo EIR is rated AC5 and built for heavy commercial use.

Can one SPC product cover both wet and dry areas?

Yes. Because the SPC core is 100% waterproof, the same product family can run through washrooms, kitchens, and dry areas without swapping to a different system.

Do I still need a separate acoustic underlay?

Often not. MILAT bonds IXPE acoustic backing rated up to 21 dB to the plank, which can satisfy impact-sound requirements without a separate underlay — confirm against your project's target.

How do I protect colour consistency across a phased programme?

Source from a single manufacturer with batch control and reserve stock for later phases when you place the order. This keeps colour and texture matched from first phase to last.

What documentation should I collect for submittals?

Typically FloorScore, CE under EU 305/2011, ISO 9001, and a product passport for traceability. MILAT provides all of these plus the wider ISO family.

Can I get a custom colour or plank size for a project?

Yes. As a manufacturer, MILAT produces custom colours and sizes to match a brand palette or setting-out grid, subject to project confirmation.

How should SPC flooring be stored on a construction site?

Flat, fully supported cartons in dry, closed rooms at reasonable temperature, away from direct sun and never stood on end. Keep it out of unheated containers during extreme weather and give it the acclimatisation period the installation guide specifies before fitting.

What site conditions must be met before installing SPC?

Wet trades finished, building glazed and at normal service temperature, and the screed tested for moisture with recorded readings within the stated limit. Installing before those points invites movement and turns any later issue into an argument about site conditions.

Why keep attic stock after the project ends?

Because future repairs need planks from the same production batch to match perfectly. A modest reserve stored flat by the client lets a damaged plank be swapped years later without hunting for a discontinued decor or accepting a visible colour difference.