How to Inspect a Flooring Shipment on Arrival

The checks to run before you sign, and what to do if something is wrong.

Buyers & Trade 8 min read Updated August 17, 2026

The half hour you spend inspecting a container when it is unloaded decides whether a problem is the supplier's to fix or yours to absorb. Once you sign clean and the claims window closes, your leverage is gone. Work through this checklist before the driver leaves and before you approve the goods for sale.

Room scene with Ottod Perfecta EIR rigid-core SPC flooring by MILAT Floor
Ottod, Perfecta EIR — one of 54 MILAT Floor designs.

Before you break the seal

Start at the container door. Check the seal number against the one on your bill of lading. If it does not match, or the seal is broken or tampered with, photograph it and note it on the delivery paperwork before opening. That single check protects you if goods have been interfered with in transit.

Count against the packing list

As pallets come off, tally the carton and pallet count against the packing list, not against memory. Confirm the number of boxes, the square metres and the pallet count all line up. A short count found now is a claim; a short count found next month is an argument.

  • Match total cartons and pallets to the packing list figures.
  • Confirm the square metres or box count per SKU if you ordered more than one.
  • Check the gross weight looks right if you have a weighbridge reading.
  • Flag any discrepancy in writing on the delivery note before signing.

Inspect carton condition

Look at the cartons themselves. Crushed corners, water staining, forklift punctures or collapsed stacks all suggest handling damage. Set aside anything damaged, open a sample of the worst cartons to see whether the planks inside are actually affected, and photograph everything before you move it. Damage to the outer carton is not always damage to the product, but you document both.

Check batch and lot numbers

Flooring is manufactured in batches, and colour and texture can shift slightly between them. Check the batch or lot number printed on the cartons and confirm the whole order shares the same batch, or that the batches match what you were told. Mixed batches installed in one room can show a visible tone difference, so you want this caught on the dock, not by an installer halfway through a floor.

Compare against your retained sample

You kept a signed sample or a reference board from the approval stage. Open a carton and compare the delivered product to it: colour, embossing, bevel, thickness, click profile and surface finish. This is the check that catches a substitution or an off-spec run. If it does not match the approved sample, stop and document before anything goes to a customer.

Surface texture of the Saccha design — rigid-core SPC plank by MILAT Floor
The Saccha decor up close.

Document and file within the window

If anything is wrong, build the file immediately: photos of the container seal, the damaged cartons and the affected planks, the delivery note with your annotations, the packing list and your batch notes. Most suppliers and insurers require claims within a set number of days of delivery, so check that window on your contract or policy and file inside it. A clear, dated, photographed claim submitted on time is almost always resolved; a late or vague one rarely is.

MILAT provides batch information and retains product references so a delivered order can be checked against what you approved. If a shipment shows an issue, contact the sales team promptly with your photos and packing list so it can be reviewed within the claims window.

Unloading is where good shipments get damaged

A surprising share of claims begin after the container doors open, caused by the receiving side. Forklift tines punched through cartons, pallets clipped against the container frame, boxes dropped on their corners because a team was rushing before rain: all of it becomes your cost, because the goods were sound at discharge. Slow the unload down. Use the right tine length, keep a spotter at the doors, and stage pallets in a marked area rather than wherever they land. If exterior damage from transit is visible as pallets come off, photograph it in the doorway, with the container number in frame, before anything moves further.

Container rain and the humidity shock problem

A steel box crossing climate zones breathes. Warm humid air inside condenses on the cold roof and drips onto cargo, a phenomenon crews call container rain, and cartons can arrive damp even though no water entered from outside. On arrival, check the top layer of cartons and the underside of the roof for moisture traces, and note any dampness on the delivery documents even if the flooring itself looks fine, since carton staining discovered later is hard to attribute. Then let the material acclimatise: pallets moved from a cold container into a warm warehouse will condense moisture on their surfaces for a while, which is normal, but stack them so air can reach the cartons.

After inspection: storage that preserves what you checked

Passing inspection means little if the warehouse then ruins the goods. SPC cartons should be stored flat and fully supported, stacked within sensible height limits so bottom cartons are not crushed, in a dry space away from direct sunlight and heat sources. Keep batches physically separated and labelled so pickers do not mix lots on a single order, which quietly manufactures a colour-consistency complaint at a customer's site. First in, first out matters too: rotating stock keeps no pallet sitting in a corner for years collecting forklift scars.

Phased shipments need a running record, not one-off checks

When a project or a season arrives across several containers, inspection becomes a series, and the value is in the continuity. Keep one register where every delivery's date, container number, batch and lot numbers, quantities and photos live together. Check each new arrival not only against its packing list but against the previous deliveries of the same product, since batch drift shows itself between shipments, not within one. If shipment three will be installed beside shipment one in the same space, lay boards from both side by side under good light before the fitters do it for you in front of the client.

Turn the checklist into a habit your team runs without you

The owner cannot meet every container. Write the inspection as a one-page routine that any warehouse colleague can execute: seal photo, count, carton condition, batch numbers, sample comparison, sign only after. Laminate it, hang it at the receiving bay, and store the photos in a shared folder named by container number. A supplier like MILAT resolves issues fastest when the evidence arrives organised, and an importer whose claims always come with clean documentation gets taken seriously on the rare occasion something is genuinely wrong. Reputation works in both directions of the relationship.

Talk to MILAT Floor

Samples, specifications, OEM & private label, wholesale or export — our team is ready.

Contact Us

FAQ

Frequently asked questions

What should I check first when a flooring container arrives?

Check the container seal number against your bill of lading before opening. If the seal is broken, tampered with or does not match, photograph it and note it on the paperwork, because that protects you if goods were interfered with in transit.

How do I verify I received the right quantity?

Count the cartons and pallets as they are unloaded and match them to the packing list, not from memory. Confirm the box count, square metres and pallet totals line up, and record any shortfall in writing on the delivery note before signing.

Why do batch or lot numbers matter?

Colour and texture can vary slightly between production batches. Confirming the order shares the correct batch numbers on the dock prevents a visible tone mismatch appearing once an installer lays planks from different batches in the same room.

What if the flooring does not match my sample?

Stop before releasing anything to customers, and compare colour, embossing, thickness and click profile against the signed reference sample you retained at approval. Photograph and document any difference, then raise it with the supplier straight away.

How long do I have to file a claim?

Most suppliers and cargo insurers set a claims window of a defined number of days after delivery. Check the exact period in your contract or policy and file inside it with photos and paperwork, because late claims are much harder to resolve.

What does MILAT need to review a shipment issue?

Send the sales team your photos of the damage or discrepancy, the annotated delivery note and the packing list, along with batch numbers. Contact them promptly so the issue is reviewed within the claims window.

What unloading mistakes cause the most flooring damage?

Forklift tines punching cartons, pallets scraped against the container frame, and boxes dropped on corners during a rushed unload. Damage created at your dock is not claimable, so a slower unload with a spotter and proper tine length pays for itself quickly.

Why are cartons sometimes damp inside a sealed container?

Condensation. Humid air inside the container condenses on cold steel surfaces during the voyage and drips onto cargo, so cartons can show moisture without any external leak. Note any dampness on the delivery documents immediately and let the material acclimatise in a ventilated stack.

Do I need to open every carton during inspection?

No. Inspect all cartons externally, then open a sensible sample from different pallets and layers, always including any carton with visible damage. Opening a spread of cartons catches systematic issues, while batch numbers and your retained sample cover consistency.